Final two pandemic-delayed BTO projects completed: HDB

Positioned along New Punggol Road, Punggol Point Cove (Phase 2) makes up 1,179 units of two-room flexi, three-, 4- and five-room flats across six home blocks. Following pandemic delays, the project’s last block was finished twelve month from its first Probable Completion Date (PCD) at an earlier time this month.

Apartment proprietors of Punggol Point Cove (Phase 2) have been receiving the keys to their new house ever since November 2024, whilst key collection for Kempas Residence commenced in mid-January this year.

The final block, that was postponed by six months from its initial PCD, was accomplished in mid-January.

The 22 home projects included 2 Shorter Waiting Time (SWT) projects, which were completed within a waiting period of much less than 3 years. The SWT work, Parc Glen at Tengah and Grove Spring at Yishun, consisted of a total of 1,995 apartments.

Minister for National Development Desmond Lee has publicized the finish of the final 2 pandemic-delayed work from HDB, according to a Jan 20 launch.

According to HDB, the finalization of Punggol Point Cove (Stage 2) marks the conclusion of all flats in the Punggol Point District. This includes Punggol Point Cove (Stage 1), Punggol Point Woods and Punggol Point Crown BTO ventures, that were completed in 2024.

Both Build-to-Order (BTO) plans, Punggol Point Cove (Stage 2) and Kempas Residences, observe the completion of HDB’s pandemic-delayed housing ventures. As a whole, the 92 projects have provided over 75,800 brand-new apartments to Singaporeans over the last 5 years.

At the moment, 110 HDB housing jobs are under development, up from 95 a year ago due to the increase in BTO supply in recent years. HDB says it is on track to accomplish around 17,000 condos across 27 ventures in 2025.

The Orie Singapore

HDB is assumed to inform the waiting flat proprietors of their key collection date shortly, following the completion of the final blocks just within both ventures this month.

Located around Serangoon Road, Lavender Road and Boon Kheng Road, Kempas Residences BTO project has 583 units of two-room flexi, three-, four-room apartments throughout four residential blocks.

In 2024, HDB completed a total of 22 home ventures, 17 of which were postponed by the pandemic. With the exception of one that was delayed due to non-pandemic reasons, the standing 4 housing plans were accomplished on schedule.

As at Jan 15, 37 households or about 7% of 555 lined up units have gathered their keys.

The remaining projects had waiting times of as much as 5 years. In general, over 18,000 flats were completed in 2024, states HDB.

As at Jan 15, 657 homes or 59% of 1,109 lined up units have picked up their keys.